Large reserves of natural gas will be extracted and processed at an offshore refinery under development at the time of our commission. Construction, which began in 2019, was more than two-thirds complete when HKA conducted its review of this challenging project for the developer/owner.
Brief
HKA was instructed to carry out an independent expert assessment of the project’s execution by the contractor. We were required to give our objective opinion on the contractor’s performance in relation to engineering, procurement, construction, and management of subcontractors.
This contractor performance review involved detailed analysis of:
- the level of manpower, both planned and actual;
- productivity, both planned and actual; and
- coordination and supervision of works by all contractors, subcontractors and vendors on and offshore.
What we did
HKA assembled a team of specialists drawn from various service areas – Forensic Technical Services; Energy, Resource and Industry; and Delay analysis. The team combined specific expertise with experience in offshore natural gas fields and skills in data analysis.
Monthly progress reports submitted by the contractor and subcontractors provided the necessary information for the performance review. The team examined all reports over a 30-month period covering all 10 work packages.
This data covered:
- planned, actual and forecast progress including both progress tables and progress s-curves;
- planned and actual manpower, both personnel numbers and worked hours, sourced from health and safety reports as well as manpower histograms; and
- areas of concern reported each month.
All this data was extracted, cleaned, processed and verified so that we could perform our analysis. This focused on various aspects, in particular:
- variances in planned versus actual manpower and progress made;
- the efficiency and productivity with which the work was done; and
- changes in reporting that indicated problems in any elements of the work packages.
The results of this analysis informed our review and assessment of the reported areas of concern. We also assessed compliance with the contractor’s obligations under the bespoke contract.
Following our initial assessment, a second delay analysis report was prepared for our client at the end of 2022.
Outcomes
Our performance review identified shortcomings in two key areas – project management and experience.
Productivity data was not provided by the contractor. We established that there was consistent progress under-achievement against the plan. This indicated that the plan was critically underestimated throughout, or manpower was insufficient.
The overall physical progress variance across the project showed there was a slow start-up followed by schedule slippage from commencement of the works. It was clear that the project would miss target dates unless mitigating actions were taken. However, underperformance continued throughout the project. Effective recovery plans were not put in place.
Key personnel lacked experience in several critical elements of the project. Underestimation of the fabrication and mobilization phases indicated a lack of personnel experience and knowledge sharing. Quality problems with certain vendors and the failure of the post-order team to conduct a thorough follow-up reflected, again, a lack of experience or insufficient resources.
Our reports will provide a robust basis for settling claims on completion of the project, now due in 2023. Grossly inflated, these amounted to US$260 million. Our reports demonstrate that the contractor is not entitled to extensions of time or prolongation costs.

"Our reports will provide the owner with a robust basis for settling claims on completion of the project."
-
ClientConfidential
-
Year2018 - 2022
-
ValueUS$1billion
-
ServicesForensic Engineering, Architectural and Technical, Claims, Expert, Delay and Disruption Analysis, Claims & Dispute Resolution
-
SectorsConstruction and Engineering, Oil and Gas
RELATED PROJECTS
RELATED PROJECTS

Subsea Cable Installation & Trenching Operations
Asia

Independent Commercial, Cost & Risk Review of Road Development
Europe

Independent Quantum Expert Review of Maintenance Contract
Europe

Major Light Rail Transit
Americas

Two New Venues
Middle East

A Major Teaching & Research Hospital
Europe

Nuclear Power Plant
Americas

New School Campus, Ultimo Primary School
Oceania

UNSW Capital Projects Sustainability Framework
Oceania

Sydney Water, Partnering for Success (P4S)
Oceania

Melbourne Airport Rail
Oceania

Liquefied Natural Gas (LNG) Project Australia
Oceania

Residential Development
Middle East

Natural Gas-Fired Power Plant
Asia

Industrial Manufacturing Facility
Europe

Subsea Power Cable Failure
Asia

Independent Quantum Expert Opinion of Highway Maintenance Contract
Europe

Subsea Interconnector Cable Failure
Europe

Energy and Telecom Cable Manufacturer
Americas & Asia

Franchise Fraudulent Transfer Matter
Americas

Clean Fuels Project
Middle East

Nuclear Power Plant Decommissioning
Americas

Global chemicals manufacturer
Americas & Europe

Home security company sale agreement
Americas

Business Park, Surrey
Europe

Highway Rock Cuttings
Middle East

Coal-fired power plant
Asia

Coal-fired power plant
Americas

Water desalination plant
Americas

WestConnex Rozelle Interchange
Oceania

Public transport service improvement
Oceania

Major Canadian Utility Commercial Damages Matter
Americas

Major Nuclear Power Plant
Americas

South American Oil Refinery
Americas

Power Plant
Americas

University of North Carolina Hospitals
Americas

Longview Power Plant
Americas

Spent Nuclear Fuel Verdicts & Settlements
Americas

Missouri Power Plant
Americas

Share our Space Program
Oceania

Lower South Creek Treatment Program
Oceania

Allseas & Pioneering Spirit
Europe

Hume Community Housing
Oceania

Infrastructure Investment Assurance Framework
Oceania

Electricity Network Improvement
Oceania

Major Transport Projects Review
Oceania

High Speed 2 (HS2) Project
Europe

Urban Transformation & Transport Programme
Oceania

Strategic Procurement & Programme Management Improvement
Oceania

Business Reform & Procurement Strategy
Australia

Sydney Metro
Oceania

Temporary School at Ultimo Primary School
Oceania

Gerald Desmond Bridge
Americas

Office and Retail Landmark
Americas

Port of Long Beach
Americas

Airport Pavement Management Survey
Americas

Greenfield St George Airport, Utah
Americas

A Giant Oilfield
Asia

Hunter River Remediation
New South Wales, Australia

Great Western Highway Widening
Victoria, Australia

Rail Rehabilitation Scheme
Bucharest to Brasov line, Romania

Yanbu Power & Desalination Plant
Yanbu Industrial City, Saudi Arabia
Follow HKA on WeChat
关注我们的官方微信公众号
